Action Roadmap

Prioritised sustainability actions · Al Quoz Industrial Facility

Total Actions

8identified
1 completed

Potential Saving

AED 2.1M/year
If all implemented

CO₂e Reduction

433tCO₂e
Annual potential

Quick Wins

4actions
Payback under 6 months

Status Overview

Action pipeline

Completed
1 actions
In Progress
2 actions
Planned
3 actions
Under Review
2 actions

Financial Impact by Action

Annual AED savings · Sorted by impact

Solar PV Installation (Rooftop)
AED 780K
HVAC Smart Scheduling & Controls
AED 410K
LED Retrofit — All Zones
AED 320K
Fleet Electrification (3 vehicles)
AED 180K
Building Envelope Insulation
AED 145K
Water Recycling System
AED 95K
Organic Waste Composting Program
AED 90K
Green Procurement Policy
AED 60K

All Actions

8 actions · Click to view details

#ActionCategoryStatusCO₂e ImpactAnnual SavingPaybackTimeline
1
LED Retrofit — All Zones
EnergyIn Progress-128 tAED 320K3 moQ2 2026
2
Solar PV Installation (Rooftop)
Renewable EnergyPlanned-94 tAED 780K1.5 yrQ3 2026
3
HVAC Smart Scheduling & Controls
EnergyPlanned-67 tAED 410K3 moQ2 2026
4
Organic Waste Composting Program
WasteCompleted-41 tAED 90K2 moQ1 2026
5
Fleet Electrification (3 vehicles)
TransportPlanned-28 tAED 180K2.3 yrQ4 2026
6
Water Recycling System
WaterUnder Review-18 tAED 95K9 moQ3 2026
7
Green Procurement Policy
ProcurementIn Progress-35 tAED 60K1 moQ2 2026
8
Building Envelope Insulation
EnergyUnder Review-22 tAED 145K2.6 yrQ1 2027